Hussain15 wrote:
It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11:00 AM, and one technician per hour is added beginning at 5:00 PM, at what time will the server be complete?

A. 7:30 PM
B. 7:45 PM
C. 8:00 PM
D. 9:00 AM
E. 10:00 PM



We should never, everrr make questions too complicated to infer and solve...
6 tech total of 10 hours... let me assume total of 60 units of work...
1 tech in 1 hr does 1 unit of work.....

11:00 am to 5:pm - 6 hours
so, total work done by 6 tech in 6 hrs will be 36 unit. ( 6*6)
now a new person gets added every hour after 5:00PM

11:00-5:00 - 36 unit
5:00-6:00 - 7 unit ( 6 tech were doing 6 unit in 1 hr, now since a new person has been added, the work increases to 7 unit)
6:00-7:00 - 8 unit ( another guy added)
7:00-8:00- 9 unit ( another guys added making total 9 person in the work field)

36+7+8+9 = 60.


so by 8:00PM 60 units of work was completed by the group....

Bingo..!!!!