machine A finish the job in 2*12 shifts = 24 shifts
machine B finish the job in 2*15 shifts = 30 shifts
Lets assume total work require 120 shifts
Therefore,
rate of A = 5 shifts/day
rate of B = 4 shifts/day
rate of (A+B) = 9 shifts/day
According to current schedule work complete in a day = 5+4+(9/2) =13.5 shifts/day
Therefore, Time required to finish 120 shifts = (120/13.5) = 8.88.. days ~ 9 days